1. Match the SketchUp object to the right quantity
A takeoff is only meaningful when the measurement matches what the modeled item represents. Mash Quantifier reads three verified source types: materials, components or groups, and tags. Each source type supports different quantity logic.
| SketchUp source | Available measurement | Typical decision |
|---|---|---|
| Material | Area or volume | Choose whether the finish or solid material is priced by square or cubic units. |
| Component / group | Piece or length | Choose whether a repeatable object is counted or measured linearly. |
| Tag | Volume, area or length | Choose the aggregate measurement that represents the tagged contents. |
Do not choose a unit only because it is available. A cabinet component may be counted by piece, while a linear profile represented by a component may be measured by length. A finish material may be priced by area, while a bulk material may require volume. The model source and commercial unit must describe the same thing.
2. Use a deliberate naming and inclusion system
Mash Quantifier identifies materials, components, groups and tags through a configured name prefix. The prefix separates items intended for takeoff from the rest of the model. This is more useful when it is treated as a project convention rather than applied randomly near the end.
Create consistent names that remain understandable in the estimate. The editable item table includes fields for name, supplier, unit, thickness, quantity and waste. A clear model name reduces the amount of interpretation required when those rows are reviewed outside the modeling context.
- Only items intended for takeoff use the configured prefix.
- Names distinguish materially different products or assemblies.
- Components represent repeatable items consistently.
- Tags collect geometry that should share one aggregate rule.
- Measurement units match the way each item is purchased.
- Thickness is recorded where it matters to identification or pricing.
The extension calculates from the structure it receives. A consistent prefix, naming convention and unit policy make the report easier to audit and maintain.
3. Separate quantity, material cost and labor cost
Quantity answers “how much?” Pricing answers “at what rate?” Mash Quantifier keeps these questions separate by providing independent material and labor prices on each item row. It also provides separate material and labor tax fields.
This structure matters because a material can change price without changing the modeled quantity, and labor can change without changing either. Keeping the rates separate makes those changes visible instead of hiding them inside one combined number.
Use waste as an explicit material decision
The waste field applies a percentage to material cost per item. Treat it as a project assumption that should be reviewed, not as a replacement for modeling or procurement judgment. Different materials can require different allowances.
Control which rows contribute to the total
Items can be selected for inclusion in the total. That allows a table to contain reference or alternate rows without forcing all of them into the current estimate. The summary separates subtotals, taxes and the overall total, so exclusions and rate changes can be checked.
| Estimate layer | Question it answers |
|---|---|
| Quantity | How much area, volume, length or how many pieces does the model report? |
| Material price | What is the rate for the purchased material unit? |
| Labor price | What labor rate belongs to this measured item? |
| Waste | What material allowance is included for this item? |
| Taxes | Which material and labor tax rates apply? |
4. Build a reusable CSV price catalog
Mash Quantifier can load a price catalog from CSV. The catalog browser can search and filter by code, category, supplier, unit and material. A reusable catalog reduces repetitive entry, but only when its entries use the same units and naming logic as the estimate.
Start with a controlled catalog rather than importing every historical price. Include enough information to distinguish similar products, verify the supplier and unit, and review prices before applying them. A price catalog is a source of rates; it does not replace checking whether the selected rate matches the modeled item.
The project estimate can also be exported as CSV for workflows in Excel and Google Sheets. CSV is the transfer format: use the spreadsheet application for additional presentation or downstream calculations while keeping the modeled quantity source understandable.
5. Keep the estimate attached to the project
Mash Quantifier stores project data inside the SketchUp file. That means the names, prices and estimate choices belong with the model instead of existing only in a separate temporary panel. This is useful for revisions, but it also makes file management important.
When the model changes, review the affected quantities and then verify the pricing assumptions that remain. Geometry can alter area, volume, length or counts, while commercial rates may need their own update. The safest review distinguishes model-driven changes from price-driven changes.
The interface supports MXN, USD and EUR. Choose the project currency deliberately and keep the imported catalog, entered rates and exported report consistent with that choice.
Save a project version before a major estimate revision and identify the date or issue of any external price catalog used. The plugin stores data with the model, but your project process should still explain where each rate came from.
6. Review the estimate as a technical document
Before using a total, check the takeoff row by row. The objective is not only to find arithmetic errors; it is to confirm that the model resource, quantity unit and commercial price all refer to the same item.
- Every included row corresponds to an intended model resource.
- Area, volume, piece and length units are used consistently.
- Supplier, unit and thickness fields identify the priced item.
- Material and labor rates are separated correctly.
- Waste assumptions are appropriate item by item.
- Material and labor taxes use the intended rates.
- Excluded rows are intentionally outside the total.
- Subtotal, tax and grand-total cards reconcile with the rows.
- Currency matches the rates and the exported report.
- The CSV opens with readable names and quantities.
A repeatable SketchUp estimating workflow therefore has three layers: organize the model for recognition, assign the correct measurement rule, and apply auditable cost assumptions. Each layer should be understandable on its own.
Frequently asked questions
What can Mash Quantifier measure in SketchUp?
Materials can be measured by area or volume, components and groups by piece or length, and tags by volume, area or length.
Can material and labor be priced separately?
Yes. Each estimate row has separate material and labor prices, along with separate tax fields for material and labor.
Which currencies are available?
The verified currency options are MXN, USD and EUR. Use one consistent currency for the project rates and report.
Can I import prices from a spreadsheet?
Mash Quantifier loads price catalogs from CSV and can filter entries by code, category, supplier, unit and material.
Where is the estimate data saved?
Project data is stored inside the SketchUp file, keeping the estimate choices with the model.
Can I use the report in Excel or Google Sheets?
Yes. Mash Quantifier exports CSV files compatible with Excel and Google Sheets workflows.